Consents

How long building consent takes, at every council

The national median is 9 working days of council processing and 16 working days total once your own responses to council questions are counted (January to March 2026). The legal maximum is 20 working days of processing time. Every consent authority is below, from MBIE's quarterly monitoring.

Total elapsed days is the number that matters to your project: it runs from lodgement to decision, including the time the clock is stopped while you answer requests for information (RFIs). Sorted fastest first.

68 consent authoritiesMBIE's official quarterly monitoring dataJanuary to March 2026 quartersource-linked below
Consent authorityTotal elapsed (median days)Council processingApplicant RFI timeMet 20-day timeframe
Kawerau5317100%
BCAL050100%
Ruapehu65498.1%
Waitomo758100%
Wellington City74196.3%
Kaikōura8512100%
Manawatu84698.4%
Consentium9125100%
Kāpiti Coast96798.4%
Carterton102594.3%
Clutha107397.9%
Far North107899%
Invercargill City1061098.2%
Tararua1081398.6%
Tasman106298.8%
Waimate1010176.3%
Buller116395.9%
Dunedin City11101398%
Marlborough117993.2%
Rangitikei118496.3%
Rotorua Lakes1179100%
Selwyn117398.4%
Whanganui1166100%
Gisborne1231098.3%
Waipa126298.4%
Waitaki12911100%
Whakatāne1258100%
Christchurch City1361199.5%
Gore1377100%
Grey139398.7%
Nelson City137899.3%
Taupō1396100%
Waikato139897.6%
New Plymouth1491298.5%
Waimakariri149597.5%
Westland1489100%
Whangārei148697.9%
Napier City1539100%
Palmerston North City156597.3%
Hutt City1611697.8%
Kaipara1698100%
Timaru163495.3%
Central Hawke's Bay1714481.5%
Central Otago1711688.3%
Masterton17141098.1%
Porirua City1713898.6%
Southland1710996.3%
Stratford179798.3%
Thames-Coromandel1791096.4%
Hurunui18131296.2%
Mackenzie1861287.3%
Matamata-Piako1812597.3%
Queenstown Lakes187690.3%
Western Bay of Plenty1815698.5%
Ashburton19131089%
Hamilton City19121098.1%
South Waikato1913498.9%
Upper Hutt City1915990.9%
Hauraki2014797.3%
Horowhenua20161096.2%
Tauranga City20101191.3%
Wairoa201214100%
South Wairarapa2191796.1%
Ōtorohanga2181383.3%
Hastings2275198.7%
South Taranaki22111597.2%
Ōpōtiki2281577.8%
Auckland28151986.2%

Source: MBIE Building Consent System Performance Monitoring, Q1 2026 (MBIE). Medians are for building consent applications; regional authorities are excluded by MBIE due to low application numbers. Consentium and BCAL are private consent authorities. MBIE calculates each column's median separately, on different sets of applications, so the columns do not add up and can look inconsistent for small authorities.

How to keep your consent fast

The gap between a council's processing days and the total elapsed days is mostly RFI time, and MBIE's analysis attributes about 66% of RFIs to missing documents, 10% to incorrect documents and 5% to misalignment between architects and engineers. Lodging a complete, internally consistent application is worth more than picking a fast council. What consents cost is on our consent fee comparison, and each council's full picture (times, fees, what slows it down) is on its own building consent page.

Can you start building before the consent is granted?

No. Carrying out restricted building work without a consent is an offence under the Building Act 2004, and unconsented work follows the property into every future LIM and sale, where it costs far more to resolve than the waiting would have. The exception is work listed in Schedule 1 of the Act: certain low-risk work, such as some small detached buildings and low decks, is exempt from needing a consent at all. Your council's own guidance, linked from its building consent page, is the place to confirm which side of that line your project sits on.

How long a consent stays valid

Getting the consent is not the end of the clock-watching. A building consent lapses if the work has not commenced within 12 months of it being granted, unless the council agrees to extend it. And once the work is finished there is a second deadline: if no code compliance certificate has been applied for within 2 years of the grant, the council must decide whether to issue one anyway. An open consent with no CCC is one of the most common problems that surfaces in a LIM years later, long after the builder has moved on.

If the council goes past 20 working days

The 20 working days is a statutory duty, not a guarantee, and the clock legally stops while an RFI sits with you. That is how a consent can be inside the law and still take months of elapsed time. The honest measure of a council is the share of consents it decides inside the statutory timeframe, which MBIE publishes and the table above shows per authority. If your application is stuck, the first question to ask the council is whether the clock is running or stopped, because the answer decides whose move it is.

Building or renovating? Check the property's title, zoning and hazard layers first.