Consents

How long building consent takes, at every council

The national median is 9 working days of council processing and 16 working days total once your own responses to council questions are counted (January to March 2026). The legal maximum is 20 working days of processing time. Every consent authority is below, from MBIE's quarterly monitoring.

Total elapsed days is the number that matters to your project: it runs from lodgement to decision, including the time the clock is stopped while you answer requests for information (RFIs). Sorted fastest first.

Consent authorityTotal elapsed (median days)Council processingApplicant RFI timeMet 20-day timeframe
Kawerau5317100%
BCAL050100%
Ruapehu65498.1%
Waitomo758100%
Wellington City74196.3%
Kaikōura8512100%
Manawatu84698.4%
Consentium9125100%
Kāpiti Coast96798.4%
Carterton102594.3%
Clutha107397.9%
Far North107899%
Invercargill City1061098.2%
Tararua1081398.6%
Tasman106298.8%
Waimate1010176.3%
Buller116395.9%
Dunedin City11101398%
Marlborough117993.2%
Rangitikei118496.3%
Rotorua Lakes1179100%
Selwyn117398.4%
Whanganui1166100%
Gisborne1231098.3%
Waipa126298.4%
Waitaki12911100%
Whakatāne1258100%
Christchurch City1361199.5%
Gore1377100%
Grey139398.7%
Nelson City137899.3%
Taupō1396100%
Waikato139897.6%
New Plymouth1491298.5%
Waimakariri149597.5%
Westland1489100%
Whangārei148697.9%
Napier City1539100%
Palmerston North City156597.3%
Hutt City1611697.8%
Kaipara1698100%
Timaru163495.3%
Central Hawke's Bay1714481.5%
Central Otago1711688.3%
Masterton17141098.1%
Porirua City1713898.6%
Southland1710996.3%
Stratford179798.3%
Thames-Coromandel1791096.4%
Hurunui18131296.2%
Mackenzie1861287.3%
Matamata-Piako1812597.3%
Queenstown Lakes187690.3%
Western Bay of Plenty1815698.5%
Ashburton19131089%
Hamilton City19121098.1%
South Waikato1913498.9%
Upper Hutt City1915990.9%
Hauraki2014797.3%
Horowhenua20161096.2%
Tauranga City20101191.3%
Wairoa201214100%
South Wairarapa2191796.1%
Ōtorohanga2181383.3%
Hastings2275198.7%
South Taranaki22111597.2%
Ōpōtiki2281577.8%
Auckland28151986.2%

Source: MBIE Building Consent System Performance Monitoring, Q1 2026 (MBIE). Medians are for building consent applications; regional authorities are excluded by MBIE due to low application numbers. Consentium and BCAL are private consent authorities. MBIE calculates each column's median separately, on different sets of applications, so the columns do not add up and can look inconsistent for small authorities.

How to keep your consent fast

The gap between a council's processing days and the total elapsed days is mostly RFI time, and MBIE's analysis attributes about 66% of RFIs to missing documents, 10% to incorrect documents and 5% to misalignment between architects and engineers. Lodging a complete, internally consistent application is worth more than picking a fast council. What consents cost is on our consent fee comparison.