January to March 2026, MBIE data
Building consent at Stratford District: how long it takes, what it costs
Stratford District processes a building consent in a median of 9 working days, and 17 working days in total once the time you spend answering the council's questions is counted. The national medians are 9 and 16 working days, so Stratford is 1 working days slower than the national median, the 46th fastest of 66 councils.
| Measure | Stratford | National median |
|---|---|---|
| Council processing timeThe statutory clock, max 20 working days | 9 days | 9 days |
| Your time answering questionsMedian applicant response to an RFI | 7 days | 9 days |
| Total elapsed timeLodgement to decision, the number that matters | 17 days | 16 days |
| Met the 20-day timeframeShare of consents processed within the statutory limit | 98.3% | 94.5% |
| Code compliance certificateMedian days to process the CCC at the end of the job | 10 days | 4 days |
Source: MBIE Building Consent System Performance Monitoring, Q1 2026 (MBIE), January to March 2026. MBIE calculates each column's median separately, on different sets of applications, so the columns do not add up.
What a consent costs at Stratford District
We have not yet verified Stratford District's fee schedule against its own published document, so we do not quote a figure here rather than guess at one. What we can tell you holds everywhere: two statutory levies apply on top of whatever the council charges, the BRANZ research levy (about $1.00 to $1.15 per $1,000 of work over $20,000) and the MBIE building levy ($1.75 per $1,000 over $65,000), roughly $550 to $580 on a $200,000 job. Fifteen councils' verified fees are in our consent cost comparison.
What actually slows a consent down
The gap between Stratford District's 9 processing days and the 17 days a consent really takes is mostly your own time answering requests for information. The statutory clock stops the moment the council asks a question and does not restart until you answer in full. MBIE attributes about 66% of those requests to missing documents, 10% to incorrect documents and 5% to misalignment between architects and engineers. A complete, internally consistent application is worth more than picking a fast council.
Compare with other councils
Southland District Council
17 working days total, 45th of 66
Thames-Coromandel District Council
17 working days total, 47th of 66
Every council, ranked: consent processing times · consent fees compared · all 66 councils · what we can check in Stratford