January to March 2026, MBIE data
Building consent at Horowhenua District Council: how long it takes, what it costs
Horowhenua District Council processes a building consent in a median of 16 working days, and 20 working days in total once the time you spend answering the council's questions is counted. The national medians are 9 and 16 working days, so Horowhenua is 4 working days slower than the national median, the 58th fastest of 66 councils.
| Measure | Horowhenua | National median |
|---|---|---|
| Council processing timeThe statutory clock, max 20 working days | 16 days | 9 days |
| Your time answering questionsMedian applicant response to an RFI | 10 days | 9 days |
| Total elapsed timeLodgement to decision, the number that matters | 20 days | 16 days |
| Met the 20-day timeframeShare of consents processed within the statutory limit | 96.2% | 94.5% |
| Code compliance certificateMedian days to process the CCC at the end of the job | 17 days | 4 days |
Source: MBIE Building Consent System Performance Monitoring, Q1 2026 (MBIE), January to March 2026. MBIE calculates each column's median separately, on different sets of applications, so the columns do not add up.
What a consent costs at Horowhenua District Council
For a residential alteration around $200,000, Horowhenua District Council charges $385 upfront. Residential additions/alterations fixed initial deposit (Section A), a flat fee regardless of value; further processing, inspections and checks are charged separately once the consent is processed. Small fixed deposit at lodgement, topped up by hourly processing and inspection fees, reconciled with a refund or additional invoice once the final inspection passes. Hourly rate: $231.50/hr.
On top of the council's own fees, two statutory levies apply everywhere: the BRANZ research levy (about $1.00 to $1.15 per $1,000 of work over $20,000) and the MBIE building levy ($1.75 per $1,000 over $65,000). On a $200,000 job that is roughly $550 to $580.
Read from horowhenua.govt.nz Building Fees & Charges (2026/27), 2026/27 schedule. Councils revise fees each July, so confirm before you budget.
What actually slows a consent down
The gap between Horowhenua District Council's 16 processing days and the 20 days a consent really takes is mostly your own time answering requests for information. The statutory clock stops the moment the council asks a question and does not restart until you answer in full. MBIE attributes about 66% of those requests to missing documents, 10% to incorrect documents and 5% to misalignment between architects and engineers. A complete, internally consistent application is worth more than picking a fast council.
Compare with other councils
Hauraki District Council
20 working days total, 57th of 66
Tauranga City Council
20 working days total, 59th of 66
Every council, ranked: consent processing times · consent fees compared · all 66 councils · what we can check in Horowhenua